Schedule for PCB Assembly order (1-10K+ units)

  • By : Project Team

Here are the common schedule for BokTech's PCBA orders from prototype to mass production (1~10K+ units).


Option #1: For PCBA sample order schedule (1-100units).

sample order schedule.png

Note:

1. This schedule is applied to PCB Assembly sample order less than <50 PCS. If the quantity is 50 to 100 PCS, it may takes extra one or two days.

2. The order will be confirmed in one day as your payment has cleared.

3. Firstly we will purchase the components locally if possible, which will shorten the materials lead time.

4. If the materials are purchased on Digikey/Mouser, there is a little risk to be held by custom clearance, this may casue a few days delayed.

5. Expedited process and expedited fee if necessary, let BokTech know when order.


Option #2: For PCBA mass production order schedule (100~10K+ units).

1494146203755894.png

Note:

1. This schedule is applied to production quantity around 1000 PCS.

- If the quantity is from 100 to 1000 PCS, it may take less 2~3 days.

- If the quantity is larger than >1000 PCS, it may take extra 2~3 days.

2. The order will be confirmed in one day as your payment has cleared.

3. Firstly we will purchase the components locally if possible, which will shorten the materials lead time.

4. If the materials are purchased on Digikey/Mouser, there is a little risk to be held by custom clearance, this may cause a few days delayed.

5. Expedited process and expedited fee if necessary, let BokTech know when order.